1
DETECT
Navisworks identifies hard interference between electrical cable tray ET-02 and mechanical HVAC duct MD-01.
2
ASSIGN & COMMUNICATE
Clash item #104 logged. Assigned to Electrical detailer with coordination note to Mechanical designer.
3
REROUTE
Elevation of cable tray ET-02 increased by +300mm in Revit to clear top of mechanical duct MD-01.
4
RE-VERIFY
Clash detection re-run executed. Zero physical conflicts reported; clearance verified.